On Monday, October 12, the Wilton City Council approved a $46,888.50 change order decrease and a $68,934.02 fifteenth payment to Triple B Construction for the Cedar Street water main replacement. The punch list work is ongoing, and the project is expected to be ready for closeout in November. City Administrator Jeff Horne announced, “This will be one of the last payments” and that the project “should finish below the engineer’s estimate.”
This item is available in full to subscribers.
Please log in to continue |
|